|
INFORMATION
SHEET 8
RISK
MANAGEMENT OPTIONS
During negotiations it has
been recognised that there are a number of circumstances in which it is
fair to review the performance of a site that has missed a milestone target,
in order to consider whether a site should still be re-certified for the
Climate Change Levy discount.
These circumstances fall
into 2 groups:
-
Firstly, there are certain circumstances
in which factors outside the control of the Participant could influence
performance. These are known as "relevant considerations".
-
Secondly, a Participant may have made
good efforts to meet the target, but have just missed the target or
alternatively a change in product mix or output level may have influenced
performance. In these circumstances, "risk management" options
apply.
Relevant Considerations
In the following circumstances
you can negotiate a milestone target failure with DEFRA:
-
Regulatory Constraints. If legislation
forces a Participant to adopt new equipment or systems that increase
energy consumption, this consumption can be added to the base line
energy performance of the site. An example of this would be some form
of environmental regulation (e.g. related to odour abatement) that
obligates the site to install new equipment (e.g. an incinerator to
remove odours from an exhaust air stream). Providing the new equipment
is properly sub-metered, the extra energy consumption can be taken
into account at each subsequent milestone.
-
Planning Constraints. If you miss
a milestone target because you cannot implement an important project
due to planning problems, then this can be considered as a justification
for missing the target. For example if a CHP project cannot proceed
either because of Local Authority planning constraints or due to problems
with obtaining a suitable gas supply.
-
Energy Supply Disruptions. The
effect of any major unexpected disruptions in energy supply can be
taken into account. Any such disruption would need to be significant
and not built in to either the base year performance or the target.
Adjustment to the figures would not be allowed, for example, for routine
interruptions to the gas supply, which were expected as part of the
supply contract. Significant changes to energy prices will not be
considered of relevance at each milestone, but may be considered in
the renegotiations allowed at the 2nd and 4th
milestones.
Risk Management
Options
In addition to the relevant
considerations described above DEFRA will changes in product mix and product
output level to be taken into consideration up to the 3rd milestone.
Product Mix and Product Output
risk management only applies to Participants with a relative target (such
as the carbon per unit output currency selected by MPMA). DEFRA accept
that the SEC of a site is strongly influenced by both product mix and
product output. For example:
-
If product output drops considerably,
the SEC usually gets worse because there are often "fixed loads"
that use the same amount of energy for any level of production.
-
If a site makes several products, each
may have a different "energy intensity" (e.g. ends and closures).
If there is a significant switch of product mix between the base year
and current milestone year this could adversely influence energy efficiency.
In these circumstances DEFRA
will consider the changes in output or product mix, PROVIDING that the
Participant can properly document the influence on energy efficiency,
using an agreed algorithmic method. For metal packaging companies this
means that a good record of product output, split by product type is required.
Also, there must be sufficient energy sub-metering and regular gathering
of energy data to show the link between production and energy efficiency.
|